Sunday, May 9, 2010

Windy Mothers Day weekend


Good thing it was a no-work weekend as the winds in Southern Maryland have been whipping for 2 days straight. Crew will return tomorrow in much calmer weather, and start right up where they left off on the upper roof-line. East & West walls are up, just need the rafters & sheathing in-between. Note the trees swayed over in the picture, even the cats didn't want to be out this weekend ! We made some final choices on the deck, porch and entry-way railing and columns on Saturday, 'many' more decisions yet to come...

Thursday, May 6, 2010

One more roof to go



A picture perfect day for the framing team. South-side of house with newly installed roof over the dining 'bump-out'. And a shot of Cleto & his dad working on the attic drop-down ladder opening in the upstairs guest bathroom. Just a few more items left on house framing besides the upper roof. Should be finished next week, then on to the garage. Welcome Tom & Kyle to the east coast. Hope you have a great time in DC this weekend and don't forget to check-out DC's newest 'tourist attraction' the newly remodeled Georgetown "Social" Safeway, the place to see & be seen in Georgetown !

Tuesday, May 4, 2010

Hump-day on the roof



Todays work included roof sheathing on street-side walls, gable & above door entry. A mighty steep pitch for Cleto!


Monday, May 3, 2010

Fabulous framing continues





2nd floor walls went up today, as did the small roof above entry door. last pix is view of house from south waterfront. We finalized our window order today, Amen !



Thursday, April 29, 2010

Framing up from 2nd deck




Less windy today, so lots of progress from Cleto & Brothers. 1st 3 pix are street view, last is den and porch looking towards river.




Wednesday, April 28, 2010

Windy day for framing






2nd floor framing today, but high winds kept the team from doing a full day on the 2nd deck. Cleto kept everyone but himself off the second floor (except for the guy that was taking the pictures :)

Saturday, April 24, 2010

1st floor framing done in under 5 days






Here's an advanced look at where the; Living room windows, Away room ('den') casements, and master bedroom bay window will be installed. Last pix is entire framing team putting up the sheathing on first floor. Go team Cleto !