Lots of action today, Walter finishing the garage bricks, team hooked up the well, ran the water & electric lines thru the foundation, poured pebbles into foundation & grated dirt around foundation. Spring is here, in the mid 60's, no sign of ospreys yet, but it won't be long.
Blog Archive
Wednesday, March 17, 2010
St. Pat's Day
Lots of action today, Walter finishing the garage bricks, team hooked up the well, ran the water & electric lines thru the foundation, poured pebbles into foundation & grated dirt around foundation. Spring is here, in the mid 60's, no sign of ospreys yet, but it won't be long.
Sunday, March 14, 2010
Weekend Rain
Tuesday, March 9, 2010
Bricks
We've had some dry & warmer [61 deg today] days during past two weeks, so Walter has been making excellent progress. Blocks and bricks for house foundation are nearly complete. He'll start on garage foundation next. Meanwhile, new crews are showing up to waterproof (white stuff called "Drylok') the interior of crawl space & install the drain tiles. Walter is currently working on the riverfront steps and Steve is waving from the crawl space under the 'away room'. Happy Birthday Molly, 3 years old today !
Subscribe to:
Posts (Atom)